| OIL
& GAS - Pluto
Woodside's 100%-owned Pluto gas
field, about 190km north-west of Karratha in Western Australia,
underpins the proposed Pluto LNG Project. The current best estimate
dry gas contingent resource is 4.1 Tcf. Another field, Xena, which
has been discovered in the same permit, has estimated gas resources
of 0.4 trillion cubic feet. Development concept for the project
includes an offshore platform, deepwater flowlines, a 36" trunkline
to shore, up to two LNG processing trains with capacity of five
to six million tonnes a year, loading jetty and associated infrastructure.
The Burrup Industrial Estate on the Pilbara coast is the selected
location for the onshore facilities.
The onshore plant is being designed
for two industrial sites just south of the existing North West Shelf
Venture which Woodside operates. Industrial Lease Area A, also known
as Site A, covers about 60ha and includes the LNG storage tanks.
Industrial Lease Area B, also known as Site B, covers about 140ha
and includes the major plant and LNG processing facilities. Of the
total area of the Pluto leases, plant and facilities will cover
about 80ha.
The onshore scope includes a reception
terminal including a pig receiver, slug-catcher and MEG (Mono Ethyl
Glycol) regeneration facility. Condensate will be stabilised and
stored onsite. Light ends will be dehydrated prior to mercury and
CO2 removal. The LNG will be transferred to two large insulated
storage tanks located on a site adjacent to the main process facilities,
and from these storage tanks along a loading jetty onto LNG tankers.
Civil works scope consists of site preparation for storage and the
plant and dredging of the shipping channel. BGC has been contracted
to do site preparation of Industrial Site A.
The engineering for the onshore portion
has been awarded to the Foster Wheeler and WorleyParsons consortium.
The Foster Wheeler - WorleyParsons group is carrying out studies
for an LNG plant using the Shell Global Solutions technology. FWW
will also design the utilities for the LNG plant, including power
generating capacity in the range of 90 to 120MW.
The Pluto fixed platform will
sit in 85m water depth, and comprise topsides weighing some 4000
tonnes plus a substantial jacket. The platform will feature minimal
facilities to minimise the operation and maintenance. It will have
no processing capability, and will feature multiple risers and J-tubes
for production and compression. The platform will act as a hub for
gas gathering from other fields. Other facilities might include
a bridge connection to a future compression platform. The offshore
FEED for the platform and facilities has been awared to the EoS
joint venture between KBR and WorleyParsons.
China's Chiwan Sembawang Engineering has won the contract to build the 8000-tonne riser platform jacket. Chiwan is also the jacket fabricator for the production platform on the Woodside-operated Angel gas project.
Pluto subsea component comprises
of a 180-kilometre 36" export pipeline, seven production wells
in water depths of between 400 and 1000 metres, two large manifolds,
and about 25 kilometres of flowlines between the manifolds and platform.
The trunkline will be routed through Mermaid Sound to a shore crossing
at Holden Point. The pipeline will
be stabilised by concrete coating and will be trenched or rock dumped
for some of its route. The shore crossing
will be trenched and backfilled to a level below the minimum tide
and will be buried for the onshore section
The engineering for the subsea trunkline and flowlines has been awarded
to J P Kenny. Allseas is set to install the
36" carbon steel trunkline with its giant new pipelay vessel
Audacia, which is being built at the Keppel Verolme yard in the
Netherlands and is due for delivery in mid-2007. The dynamically-positioned
Audacia will be 225 metres in length and 32 metres wide. Pipeline
installation will be targeted for late 2009.
Aker Kvaerner had been awarded a Nkr105 million (US$19.1 million) contract to supply steel tube umbilicals. The contract follows an announcement that Aker Kvaerner had signed a three-plus-one-plus-one-year frame agreement with Woodside to become the Australian oil and gas giant's preferred supplier of steel tube umbilicals. The contract is for the supply of 28 kilometres of static umbilicals to the Pluto gas field. The umbilicals will be manufactured and delivered out of Aker Kvaerner Subsea's facility in Moss, Norway. Delivery is scheduled for July 2009.
Grenland Group has signed a letter of intent with FMC Technologies in Kongsberg for the fabrication, assembly and testing of subsea structures that will be part of FMC's delivery. The contract has a value of approximately NOK 70-75 million in revenue to Grenland Group. The subsea structures to be fabricated and assembled by Grenland Group, will have a total weight of over 700 tonnes. The subsea structures shall be fabricated at Grenland Group`s yards in Grenland, Norway. The delivery of the subsea structures is scheduled for spring 2009.
Woodside Petroleum has approved the A$11.2 billion (US$9.8 billion) Pluto liquefied natural gas project in Western Australia on 27 July 2007. Work on the project has been underway since December 2006 when the board approved initial funding for long lead items and site preparation. Site preparation has been underway since January 2007, after Woodside received environmental and heritage approval to begin work on the project’s storage tanks and export facility. Preparation works for the gas processing plant, where the production train will be located, also began.
The project will create up to 3000 direct jobs
during construction and up to 200 jobs during operations. A further
3000 indirect jobs will also be created, mostly in Western Australia.
LNG shipments could begin from late 2010, targeting the Asia-Pacific
and North American markets.
|