| OIL
& GAS - North Rankin Redevelopment (NR2)
Woodside Energy Ltd as an operator
of the North West Shelf Venture (NWSV), together with its six equal
participants in the NWSV have began studies on the North Rankin
Redevelopment (NR2) which involves the construction and installation
of a new platform North Rankin B (NRB) and modification of the process
modules of NRA. NRB will be installed alongside NRA with a bridge
linking the two platforms.
The prime function of NRB
is to provide gas compression and condensate pumping for hydrocarbons
produced by the NRA wells, to maintain production and to recover
remaining reserves. NRB will extend the life of the North Rankin
and Perseus fields to 2041. Following
installation of the new NRB platform, the two platforms will function
as one production complex.
The NRB topsides will be
approximately 20,000 tonnes and will be installed by float over.
The deck is supported by a 23,000 tonne eight leg, cross-braced,
steel structure jacket with drilled and grouted piles on each corner.
The NR2 project also has extensive Brownfield scope as a result
of the process/utility ties between the two facilities and major
maintenance requirements to meet the extended life of NRA.
FEED and procurement of
long lead items for NR2 will begin in the first quarter of 2007.
The engineering, procurement management and construction management
support services contract for FEED only was awarded to the Eos Joint
Venture, an unincorporated joint venture of WorleyParsons Services
Pty Limited and KBR E&C Australia Pty Ltd.
|